TOP-DCORD: Die Change Orders

 Rev: 09/27/05

Scope:  This procedure covers die changes ordered by customers.   A Die Change Order (DCO) is the process of making customer requested changes to dies which affect the configuration of the final forgings.

 

STEP

WHO

WHEN

INFO TO USE

WHAT TO DO

RESULTS

1 Anyone Upon receiving customer request for a die change Customer request, customer prints Forward information to Customer Service Rep and copy Vice President Sales Sales department aware of die change.
2 Customer Service Rep Upon receiving customer request for a die change Customer request, customer prints Initiate a quote with blue copy, next change open order to hold status and forward to Engineer Quote initiated and forwarded to Engineer; open orders, put on hold
3 Engineer Upon receiving quote blue copy Quote blue copy, prints, customer info Review quote and note if a DCO (Die Change Order) will be required, finish quote per TOP-QUOTE; forward to VP-Sales Quote complete, DCO noted and forwarded to VP-Sales
4 VP-Sales or Customer Service Rep Upon receiving quote blue copy Quote blue copy, prints, customer info Get customer approval (obtain their PO) to proceed with DCO; enter DSN for die change upon approval; computer will generate DCO number Customer approval and DCO started; all notified via computer if DCO in process
5 Engineer* Upon receiving DCO DCO; Engineering file Decide if existing drawing needs to be revised or if a new drawing is needed; initiate TOP-PRINT in either case; if pattern or tracing model needs to be created or revised, have work done and approved per TOP-PATRN and TOP-MODEL; as soon as possible, prepare or revise any affected die layout, die drawings or machine prints (all per TOP-PRINT; if deemed appropriate, solicit die sinker quotations and initiate sinking of dies per TOP-SINKR; estimate any change to material size and such, and immediately update Steel Size change in die cards with explanations of update; initiate Job Order for Die and/or Tooling. Forging, die and machine drawings created or revised as needed (approved with prints distributed as part of TOP-PRINT; approved pattern and/or model created or revised as needed; die sinker quotations and follow- through as needed; DCO completed; Job Order for Die and/or Tooling initiated; material changes updated with explanation in die cards.
6 VP-Quality & Engineering Upon receiving notification of Job Order for Die and/or Tooling entry from computer Job Order for Die and/or Tooling As needed work with Engineer, Production Supervisor and Machining Div. Manager if machined, to determine approach to job, layout of die, etc.; as soon as possible get dies in process per TOP-SINKR (or TOP-IMPTL if simple change); when dies are ready, as needed have die impression casts made and approved per TOP-CASTS ; as new or reworked die is tried out, ensure any improvements made are recorded per TOP-IMPTL; Job Order for Die and/or Tooling reviewed, completed and initiated Dies redesigned and prepared as needed; Job Order Die and/or Tooling issued for die change

 

 

For information on a document or record, including definition, primary responsibility and retention, refer to the Document and Record Master List.

Documents are controlled only when viewed on-line in the original English -- printed copies or translations are not controlled documents.
© 2008 Trinity Forge, Inc.,  +1 817-473-1515