STEP |
WHO |
WHEN |
INFO TO USE |
WHAT TO DO |
RESULTS |
|
1 |
Machining
Department Manager |
Upon review of daily
schedule showing newly released Job Orders |
Shop
Schedule (Machining) |
Review Job Order to be sure all necessary info is present; add operation's steps to the Router (may involve research to determine steps); forward PO revision to Machining Clerk |
Job Order and Schedule
reviewed |
|
2 |
Machining Clerk |
On receipt of Job Order |
Machining Job Order; Machining Schedule; MPS; print; possibly other documentation |
Call up and review rough MPS, determine if any changes are needed to the MPS's operation orders or inspection orders per Job Order or
to prints modified via e-mail, and make any needed MPS changes (other than "cover sheet" data) per TOP-MPSMM; update the MPS's "cover sheet" to reflect the specifics of the current order; print the whole MPS packet; pull
print from Print Viewer; check for revision level and insert in packet; have
the Machining Department Manager, Programmer or Supervisor review and sign-off on
the MPS cover sheet when the MPS packet is set up ;
after securing approval, file the packet in the Machining Job File. |
Up-to-date MPS; job packet of Machining Job Cover
Sheet, Operation, and Inspection Orders (with page 1 of Inspection Records)
printed and held; MPS approved and filed |
|
3 |
Machining Clerk |
Upon review of Machining
Department Schedule for jobs scheduled to
start within two weeks |
Machine Shop Schedule |
Pull the folder for each job being released and make any changes needed to bring the information up to date; return the cover sheet to the Machining Job File; build a job packet for each operation by adding copies of prints, NC program hard copies, weld logs and any other documents needing to go to the Machine Operator, Welder, QC Inspector, Crib Attendant or Material Handler |
Job verified as starting soon; job packets released to Crib Attendant; MPS cover sheets
made |
|
4 |
Programmer |
As receive copy of Machining
Department Schedule |
MPS; print; NC program (if any) |
Review documents and program for revision level; determine what, if any, changes are needed, and, if so, modify CAM file.
Generate NC program and NC code file; move NC code file for the operation in the
"approved-to-run" directory. The NC program should contain the following
information; Die#, DSN#, Revision, Machine#,Operation# and variation code if
needed. Print the NC code file out as the "hard copy" and insert hard copy
of the printed program in the operation's job packet; update the MPS if needed
to reflect any program changes. |
CAM files, NC program and Operation Orders updated and revision levels synchronized; hard copy of the printed program waiting for operator |
|
5 |
Material Handler |
Daily |
Current Machine Job list;
Shop Floor Travelers; product received from traffic |
Verify that all paperwork and tags are complete and appear to be correct;
transfer parts as needed to processing containers (while parts are being transferred, place container
tag on the container you are transferring into; if container tags do not come out
even, make or destroy extra QC tags); deliver material to the machines per TOP-MOPPP
or to Material Storage
racks if not immediately needed for production. |
Incoming material coordinated with shop needs |
6 |
Tool Crib Attendant |
As receive new job packets |
Information in job packet, Current Machine Shop Schedule |
Go through the needs of each operation and kit the tools and supplies needed for each operation; notify Tool Maker of any needed fixtures or other tools; coordinate with QC Inspector to be sure all inspection equipment is ready for the job; if
resources are not available or may impact the scheduling of the job, notify the
Machining Manager or Supervisor. |
Operations are kitted and shortages are identified; Tool Maker informed of tool and fixture needs |
7 |
Tool Maker |
Upon notification that tool or fixture work is needed |
Verbal notification; prints; Machining
Department Manager's instructions |
Work with Machining
Department Manager, and others as needed, to determine what tools and fixture work is needed, and when it is needed; acquire the necessary materials and produce the tools and fixtures; secure Shop Floor Traveler for tooling work from Machining
Department Manager or Supervisor; mark all pieces with the die
number; turn the tools
over to the Crib Attendant and fixtures to Material Handlers. |
Tools produced to Machining
Department Manager's satisfaction and submitted to Crib Attendant
and Material Handler |
8 |
Machining
Department Clerk/ Supervisor |
As time is approaching for an operation to begin (typically several hours ahead) |
Own judgment; Machining Schedule; job packets |
Verify that print revision is the correct one for the order; notify the operator that the job is nearly ready to begin and verify that the preparations are complete (be especially careful that the machine choices on Shop Floor Traveler are current). |
Operator notification and any final verification done in a timely manner |
9 |
Operator* |
Upon Machining
Department Manager/Supervisor's notification that a new operation is to be initiated shortly |
Machining
Department Manager/Supervisor's verbal notification; job packet |
Get operation's job packet
and kit from Tool Crib; verify that the preparations for the job are complete and that the documents seem to be complete; check to be sure the kit appears to be correct and complete; If kit tag has a green dot, then kit is complete. Red dot indicates that kit is incomplete. Refer to kit tag for items that are short. Notify NC Programmer need for program download. Review the job for ideas and questions. |
Operational and QC documents ready to go to the
machine with tools and fixtures; NC Programmer notified |
10 |
Programmer |
As receive notification of need for program download |
Machine
Department Schedule; Supervisor's
instructions |
Prepare NC file for download; verify NC file header information matches information on Machine schedule; verify all switches are set to send to appropriate machine; verify machine received
program(s) and that there were no send or receive errors |
Program sent to machine and verified |
| 11 |
Operator* |
When time comes to run a new job |
Machining
Department Manager/Supervisor's verbal notification; Operation Order; Inspection Order and rest of job packet for machining |
Get the kit for the operation you are to machine;
check to be sure you have everything you will need for the job, including material and NC program (if any); verify that all documents match the Operation Order (this includes prints - check revision level --, hard copies and photos); verify that the work pieces and container tags match the print and Operation Order; resolve any questions or suggestions with your Supervisor; set up and run the job per TOP-MOPPP when complete check job packet with last machined part from QC; return kit and unused materials back in with Crib Attendant to close out the operation(s). |
Operation initiated, machined and closed out with materials returned to crib |
12 |
Machining Manager |
Upon receiving job packet documents back after operations complete |
Operation Order, Inspection Order, and rest of job packet from machining; MPS; Shop Floor Traveler; Weld Logs; |
Verify that operations have been completed to standards set out in MPS;
review counts for accuracy; review materials issued to job; consider how the job might be improved next run; consider what steps can be taken to prevent potential problems in future runs; decide if a change is indicated for the MPS and, if so, initiate MPS change per TOP-MPSMM; forward completed packet to Machining Department Clerk. |
Results of operation verified; improvements to job sought; MPSs
maintained to reflect experience and improvements |
13 |
Machining
Department Clerk |
Upon receiving job packet documents back after operations complete |
Operation Order, Inspection Order, and rest
of job packet from machining or subcontracted operation; MPS, Weld Logs |
Discard duplicate print copies; scan all
pertinent document into the Shared Directory for retention per
TOP-RECDS. |
Job documents held as records of the job |
14 |
Material Handler |
As jobs are complete or at a semi-finished hold |
Shop Floor Traveler;
Operation Order |
If job to be warehoused,
mark part count on container; ensure that the product is securely packaged, properly tagged (or marked), and protected from deterioration; if the parts are to be warehoused for longer than one week ensure that they are
tagged and dated with the date they are warehoused and that there is an Operation Order addressing their warehousing and preservation. |
Parts warehoused short- or long-term |
15 |
Material Handler |
At least once every 3 months |
Date on Container |
Check machining division for stored machined parts. If box date is 3 months old or older, open and check parts for damage and deterioration. If parts are in good shape, stamp boxes with review stamp, inspection id, and the date. If damage is found on a machined part, notify Machining
Department Manager immediately; perform steps as instructed by Machining
Department Manager; upon completion of part repair, stamp boxes with review stamp, inspection id, and the date. |
Machined parts
monitored in Warehouse |
16 |
Machining QC Inspector |
Upon final inspection |
Inspection Order; print;
Shop Floor Traveler |
Verify that Inspection Order, print, parts and tags match; fulfill inspection requirements specified in Inspection Order and record results on Inspection
Order; coordinate with Operator or Material Handler to resolve any problem or question, bringing Supervisor or Manager in as deemed appropriate; for any nonconforming parts identified, initiate a Discrepancy Report and
retain for Machine Department Manager per TOP-MOPPP; if non-conforming parts are found and are
re-workable, then disposition will be made to rework; if a partial has been sent to
Shipping, then QC will recall all parts for 100% inspection. |
Parts inspected and discrepancies resolved; Inspection Records maintained; Discrepancy Reports produced as necessary |
17 |
Machining QC Inspector; Material Handler |
As jobs are ready to ship
or return to Traffic for additional processing |
Shop Floor Traveler; rest
of job packet |
When satisfied that product, documentation, packaging, preservation, tagging and marking are correct, sign off on the "machining" step of each container tag to approve the product for sealing and delivery;
Stamp each container with green Machined stamp; mark part count and location on the face of the Shop Floor Traveler, along with the scrap count; notify
Shipping Dept; stage product to be picked up by
Shipping and shipped per TOP-FINIS;
on final shipment, give all documents in job packet to
Machining Manager for final review. |
Parts verified ready to ship and shipped; MPS cover sheet updated; shipping paperwork to
Machining Manager |
18 |
Machining
Department Clerk |
As jobs are shipped |
Shipping paperwork; Shop
Floor Traveler; saved MPS cover sheet |
Discard duplicate print copies; scan all pertinent
document into the Shared Directory for retention per
TOP-RECDS; when final
shipment has been made, review labor entries for accuracy and correct as
necessary. Complete Job Order status where appropriate. |
Complete packet of machining job records verified for completeness and filed |